Ombudsman recommends that Commission pay subcontractor under Galileo project after long delays (link)

Published on
March 21, 2005
Last updated
May 22, 2015

Strasbourg, 18 March 2005

Draft recommendation to the European Commission in complaint 530/2004/GG. Strasbourg, 11 March 2005

The complainant, a small German company, took part in lot H (Galileo Market Observatory - GMO) of the Galilei project as a sub-contractor of ESYS, the principal contractor. The project co-ordinator was a company called GAIN S.A...

The complainant alleged that there had been considerable delays in payment which had caused it severe financial problems.

It made the following claims:

(1) The Commission should release the 15% of the contract sum retained by it and transfer the amount of EUR 12 948,06 to the project co-ordinator or to ESYS;

Âé¶¹

ADVERTISEMENT

(2) The Commission should pay to the complainant interest on account of late payment for delays exceeding the period of 60 days foreseen in the contract.

[...]

Conclusion

In view of the above, the Ombudsman makes the following draft recommendation to the Commission, in accordance with Article 3 (6) of the Statute of the Ombudsman:

Âé¶¹

ADVERTISEMENT

The Commission should compensate the complainant for the negative effects of its delay in handling cost statements nos 2 and 3.

The Commission and the complainant will be informed of this draft recommendation. In accordance with Article 3 (6) of the Statute of the Ombudsman, the Commission shall send a detailed opinion by 15 June 2005. The detailed opinion could consist of the acceptance of the Ombudsman's decision and a description of the measures taken to implement the draft recommendation.

linkname:European Ombudsman

Âé¶¹

ADVERTISEMENT

Register to continue

Why register?

  • Registration is free and only takes a moment
  • Once registered, you can read 3 articles a month
  • Sign up for our newsletter
Please
or
to read this article.

Sponsored

Featured jobs

See all jobs
ADVERTISEMENT